- Heavy construction machinery moving onto the site of the future Gregg Museum.
After the ceremonial groundbreaking on April 14, 2015, official construction on the new Gregg Museum started June 1. Bulldozers, concrete trucks, and other heavy machinery made their way onto the site at 1903 Hillsborough Street and after sixth months, much of the site demolition has been completed. Though rain and site conditions have delayed the project a little, the foundation of the new addition is close to completion. Drainage systems and waterproofing of the existing home are currently going in and we hope to see the steel supports erected on the new addition soon.
- The beginning of grubbing and clearing the construction site for the new Gregg Museum facility.
- July 15, 2015
- The hole being dug and cleared for the foundation of the addition to the 1920’s residence.
- August 6, 2015.
- Foundation footings being dug and foundation walls being formed for the 15,000 square foot addition to house the Gregg Museum permanent collection and galleries.
- September 14, 2015.
- One of the many rainy days that has set construction back a little.
- October 1, 2015.
- A view over the formal garden to a concrete truck pumping concrete into the foundation wall forms.
- November 12, 2015.
- A concrete pumping truck filling the foundation walls.
- November 12, 2015.